Snagging a New Home in Dubai: What to Check Before You Accept the Keys
A new home in Dubai is handed over with a date, a set of keys and a form to sign. Snagging is how you find the defects that form does not show, while they are still the developer's to fix. Here is when to snag, what a thorough inspection covers and how to follow the list through to the end.
Last updated: 14 November 2026
Key takeaways
- Snag after the developer invites you to inspect and before you sign the handover acceptance.
- Check every room and system: air-conditioning, plumbing, electrics, waterproofing, finishes, joinery and appliances.
- Under Article 40 of Dubai Law No. 6 of 2019, developers remain liable for structural defects for ten years and for defective installations for one year from handover.
- A snag is closed only when someone has re-checked the repair, not when the contractor says so.
What snagging is, and why it matters in Dubai
A snag is a defect or unfinished item: a chipped tile, a door that does not close, a socket with no power, a missing seal. Snagging is the structured inspection of a newly built or newly handed-over home to record every one of those items, so that the developer or contractor repairs them.
In Dubai the stakes are higher than in many cities. Homes are often bought off-plan and handed over in large batches, so finishing teams work at speed. The climate is unforgiving: a weak waterproofing detail or a poorly installed drain line becomes a visible problem within months, not years. And many owners are abroad at handover, which means the inspection is either delegated or skipped.
When to snag: before you sign
The best moment is after the developer invites you to inspect, and before you sign the handover acceptance. At that point the home is empty, every surface is visible and the obligation to fix is clear.
If you have already taken the keys, snagging is still worthwhile. Record everything as early as possible, in writing, and keep the date. A second inspection a few weeks after moving in, once the air-conditioning and plumbing have run under real use, often reveals issues an empty home hides.
What a thorough inspection covers
A proper snagging inspection is methodical, room by room and system by system. As a minimum, it should cover:
- Air-conditioning — every unit switched on and checked for cooling, airflow, noise and thermostat response. Condensate drains and drip trays checked, because blocked drains are a common source of ceiling stains.
- Plumbing — water pressure and hot water at every tap and shower, drains run for several minutes, toilets flushed repeatedly, visible joints checked for weeping, and continuous silicone around baths, showers and basins.
- Electrical — every socket tested, every switch and light operated, the distribution board labelled and its protective devices tested, including outdoor lighting and smart-home controls.
- Waterproofing and drainage — balconies, terraces, roofs and wet areas checked for falls towards the drain, standing water and staining; in villas, garden and paving drainage too.
- Floors and walls — tiles checked for cracks, chips, uneven edges and hollow sounds; paint and plaster for patches, cracks and overspray; ceilings for staining.
- Joinery, doors and windows — every door, wardrobe and drawer opened and closed; window and sliding-door seals, locks and handles checked; frames inspected for gaps.
- Kitchen and appliances — each appliance switched on, cabinet doors aligned, worktop joints sealed, extractor working.
- Villa extras — pool equipment and plant room, irrigation, boundary walls, gates, roof access and any lift.
Where specialist testing is needed, such as thermal imaging to trace a hidden leak, it should be agreed in advance and carried out by a qualified inspector.
Documents to ask for at handover
The paperwork matters as much as the finishes. Before you sign, ask for:
- Warranties for the air-conditioning, appliances and any waterproofing, with start dates
- Operation and maintenance manuals for the systems in the home
- A key and access-card inventory, signed by both sides
- Meter readings on the day of handover
- Contact details for the developer's defects or customer-care team, and the process for raising items
Your position on defects
Dubai law gives owners real protection, and it is worth knowing before you sign. Under Article 40 of Dubai Law No. 6 of 2019, which governs jointly owned real property, the developer remains liable for ten years from the project's completion certificate to remedy defects in the structural parts of the property. It also remains liable for one year from handover of the unit to repair or replace defective installations, including mechanical and electrical works and sanitary and sewerage installations. If an owner does not take possession, that one-year period runs from the completion certificate. The same article states that agreements made after the law came into force that contradict these provisions are void.
How this applies to a specific unit or villa depends on the project and your contract, so take legal advice if a dispute develops. In practice, the one-year installations period is the window that matters most: it is why a second inspection during the first months is so valuable.
From snag list to a closed list
Finding defects is the first half of the work. Closing them is the second, and it is where most owners lose momentum.
- 1. Number and photograph every item. Each snag gets a number, a room, a short description and a photo. Vague items ("paint issues, living room") are easy to dispute.
- 2. Submit the list in writing, through the developer's official channel, and keep the confirmation.
- 3. Agree access and timing. Contractors will need entry; decide who lets them in and who stays while they work.
- 4. Re-inspect every repair. A snag is closed only when someone has checked it, not when the contractor says so. Photograph the result.
- 5. Keep the file. Note dates, names and outcomes. If the same fault returns inside the warranty period, you will have the history.
Snagging when you are abroad
Many owners collect keys from another country. In that case, appoint one person to act for you: someone who can attend the inspection, submit the list, supervise access for repairs and send you a clear update with photos. Give them written authority from the developer's side if required, and agree in advance what they can approve without you.
How SETTRA helps
Our snagging and handover inspection service covers the whole route: we carry out the inspection, compile the numbered list, submit it, coordinate access for the developer's teams and follow up until each item is resolved, with photo updates in writing. If you are abroad, we act as your representative on the ground. It is also part of our renovation and fit-out management.
After handover, many owners move straight into residence care while they are away, so the home is checked regularly while it settles in. If you are planning works next, read our villa renovation guide and setting up DEWA, Ejari and internet.
Ask SETTRA a question about your own situation.
FAQ
What is snagging in Dubai?
Snagging is a detailed inspection of a newly built or newly handed-over home to record defects and unfinished items, from finishes and fittings to air-conditioning, plumbing and electrics, so the developer or contractor fixes them before or soon after handover.
When should snagging be done?
Ideally after the developer invites you to inspect and before you sign the handover acceptance. A second inspection in the first months of living in the home is also useful, because some faults only appear once the systems are in daily use.
Is a snagging inspection worth it for a new apartment or villa?
For most owners, yes. A methodical inspection records issues that are easy to miss on a quick walk-through, and a written, photographed list makes it far easier to hold the developer to repairs during the defect liability periods.
How long is a developer liable for defects in Dubai?
Under Article 40 of Dubai Law No. 6 of 2019, a developer remains liable for ten years from the completion certificate for structural defects, and for one year from handover for defective installations such as mechanical, electrical, sanitary and sewerage works. Take legal advice on how this applies to your property.
Can someone snag my home if I am not in Dubai?
Yes. A representative can attend the inspection, submit the list, supervise access for repairs and report back with photos. Agree their authority with you and the developer in writing beforehand.